POLITICS

Crown corporation steps in to do work at Muskrat Falls amid safety concerns

04/29/2015 08:27 EDT | Updated 08/04/2015 09:59 EDT
ST. JOHN'S, N.L. - The Newfoundland and Labrador government says Nalcor Energy has taken over the work of an electrical sub-contractor at the Muskrat Falls construction site after a stop-work order was issued amid safety concerns.

The government says the Crown corporation will conduct the work until the Labrador-based sub-contractor can show it is complying with health and safety obligations.

No injuries were reported as a result of the safety concerns.

The main contractor at the site, Astaldi Canada, says the temporary shutdown of the construction site in central Labrador resulted in excess water accumulating at the lower section of the hydroelectric pumphouse.

Astaldi says water is not affecting the integrity of the structure or the safety of workers at the site.